A
AcadiFi
Revenue RecognitionHard

Bridgewater Construction has a $50 million fixed-price contract to build a warehouse. At the end of Year 1, costs incurred to date are $18 million, estimated total costs are $40 million, and progress billings are $20 million. Under the percentage-of-completion method (over time recognition), what contract asset or liability should appear on the balance sheet?