Vanguard Engineering signs a $2 million construction contract with a $200,000 completion bonus. The probability of earning the bonus is 70%. Under the IFRS 15 constraint on variable consideration, what amount of variable consideration should Vanguard include in the transaction price if the completion timeline is highly uncertain?